The Distribution Waterfall — Hurdle, Catch-Up and Carried Interest as Arithmetic
A distribution waterfall is the order in which an AIF's proceeds are shared between investors and the manager. This lesson explains the hurdle rate, carried interest and catch-up, and works one full example step by step. All terms in the examples are invented for arithmetic only.
What a waterfall is
When an AIF sells its investments, the money has to be divided between the investors and the manager. The distribution waterfall is the agreed order in which that happens, stage by stage.
SEBI does not prescribe the waterfall. The waterfall, the hurdle rate and the carried interest are contractual terms set in each fund's placement memorandum, and they differ from fund to fund. What SEBI does require is that the placement memorandum illustrate the waterfall with a worked example, so that an investor can see how the fund's own terms operate.
The building blocks
A hurdle rate, also called a preferred return, is the return investors must receive before the manager earns any share of profit. If investors' return does not exceed the hurdle, the manager receives no profit share. The hurdle is not a promised return: it only sets the order of payment if there is enough money.
Carried interest, or carry, is the manager's share of profits. It is separate from management fees and expenses, which are charged in addition.
A catch-up clause, if a fund has one, comes into play after the hurdle has been paid. It gives the manager a larger share of the next slice of proceeds until an agreed split of total profit is reached.
With and without a catch-up
The catch-up changes what carry is measured on. Without a catch-up, carry applies only to the profit above the hurdle. With a full catch-up, the manager ends up with the agreed percentage of the fund's total profit. On the same proceeds, a catch-up therefore gives the manager more and investors less.
What the arithmetic assumes
The examples in this lesson use made-up terms and assume the fund has made a profit. Real terms differ. A fund may also make no profit at all, in which case there is nothing to share and investors may get back less than they contributed.
Rules at a glance
When the hurdle is not crossed
The terms here are those of this example only. Investors contribute ₹200 crore to a fund. When it winds up it has ₹230 crore to distribute, and on the fund's terms the hurdle works out to ₹40 crore.
Total profit is ₹230 crore − ₹200 crore = ₹30 crore, which is less than the ₹40 crore hurdle. Investors receive the whole ₹230 crore and the manager receives no carried interest. The hurdle was never a promise, only a threshold the manager had to cross before sharing in profit.
A waterfall with a full catch-up
- Terms of this example only: investors contribute ₹200 crore. When the fund winds up it has ₹290 crore to distribute. Investors first receive their capital and then a hurdle that, on the fund's terms, works out to ₹40 crore. The manager then has a full catch-up so that its carried interest ends up equal to 20% of total profit; anything left is shared 80% to investors and 20% to the manager. Management fees and expenses are ignored.
- Total profit: ₹290 crore − ₹200 crore = ₹90 crore.
- Stage 1, return of capital: investors receive ₹200 crore. Left to distribute: ₹90 crore.
- Stage 2, hurdle: investors receive ₹40 crore. Left to distribute: ₹50 crore.
- Stage 3, catch-up: the manager receives ₹10 crore. At that point profit of ₹50 crore has been paid out (₹40 crore + ₹10 crore) and the manager has 20% of it: ₹10 crore ÷ ₹50 crore = 20%. Left to distribute: ₹40 crore.
- Stage 4, the rest: investors receive 80% × ₹40 crore = ₹32 crore and the manager 20% × ₹40 crore = ₹8 crore.
- Totals: manager ₹10 crore + ₹8 crore = ₹18 crore, which is 20% × ₹90 crore. Investors ₹200 crore + ₹40 crore + ₹32 crore = ₹272 crore. Check: ₹272 crore + ₹18 crore = ₹290 crore.
Result. With a full catch-up the manager's carried interest is ₹18 crore and investors receive ₹272 crore. Without a catch-up, carry would apply only to profit above the hurdle: 20% × (₹90 crore − ₹40 crore) = ₹10 crore, and investors would receive ₹280 crore.
Key points
- The waterfall, hurdle rate and carried interest are contractual terms in the placement memorandum, not SEBI figures.
- The placement memorandum must illustrate the waterfall with a worked example.
- Hurdle rate (preferred return): the return investors must receive before the manager earns carried interest; it is not a promised return.
- Carried interest is the manager's share of profits; management fees and expenses are charged separately.
- A catch-up clause, if a fund has one, raises the manager's share after the hurdle until an agreed split of total profit is reached.
Common misunderstandings
- SEBI does not set a standard hurdle rate or carry percentage: both are contractual terms in each fund's placement memorandum.
- A hurdle rate is not a guaranteed or promised return: it is the return investors must receive before the manager earns carried interest, and a fund may fall short of it or lose money.
- Carried interest is not the manager's only income from the fund: management fees and expenses are charged separately.
Questions people ask
What happens if the fund's profit is below the hurdle?
No carried interest is paid: if investors' return does not exceed the hurdle, the manager is not entitled to a share of profits.
Where can an investor see how a particular fund's waterfall works?
In the fund's placement memorandum, which sets the terms and must illustrate the waterfall with a worked example.
Why does a catch-up change the manager's share?
Without it, carry is calculated only on profit above the hurdle. With a full catch-up, the manager ends up with the agreed percentage of total profit.
What this lesson relies on
- SEBI Master Circular for Alternative Investment Funds, 3 June 2026 (as updated)
- SEBI (Alternative Investment Funds) Regulations, 2012 (as amended to 14 July 2026)
This lesson was reviewed independently against these sources on 8 October 2026. Rules change: check the current regulation, scheme document or policy wording before relying on any figure. This is education, not advice.

